A can complete 1/4 of a work in 5 days and B can complete 1/5 of the same work in 6 days. In how many days can both A and B together complete the work?
Options:
- A: 10 days
- B: 12 days
- C: 15 days
- D: 18 days
Related Practice Questions:
- Which of the following artifacts, extensively found at Burzahom and Gufkral, specifically indicates that the Neolithic inhabitants of Kashmir practiced sewing animal skins for clothing to survive the harsh winters?
- The earliest known evidence of rock art in India, in the form of 'Cupules' (hemispherical cup-shaped depressions carved into rock), belongs to the Lower Paleolithic age and was found at:
- The first human colonization of the fertile Ganga plains, as evidenced by archaeological discoveries at Sarai Nahar Rai and Mahadaha, took place during which period?
- Which prehistoric site located in the Thar Desert of Rajasthan provides a continuous and undisturbed profile of Lower, Middle, and Upper Paleolithic cultures?
Loading Preview