A contractor undertook to complete a task in 150 days and employed 200 men. After 50 days, he found that only 1/4 of the work was completed. How many more men must he employ to complete the work exactly on time?

Options:

  • A: 50 men
  • B: 100 men
  • C: 150 men
  • D: 300 men