A completes half of a piece of work in 5 days, while B completes one-third of the same work in 5 days. They work together for 5 days, after which A leaves. How many days will B take to complete the remaining work alone?
Options:
- A: 2 days
- B: 2.5 days
- C: 3 days
- D: 4 days