With reference to Public-Private Partnership (PPP) models in Indian infrastructure, consider the following statements: 1. In the Engineering, Procurement, and Construction (EPC) model, the entire financial risk and investment are borne by the private developer. 2. In the Build-Operate-Transfer (BOT) Toll model, the private developer is responsible for financing, constructing, and operating the project, and recovers investment through toll collection. 3. The BOT (Annuity) model eliminates traffic risk for the private developer as the government pays fixed annual payments. Which of the statements given above are correct?
Options:
- A: 1 and 2 only
- B: 2 and 3 only
- C: 1 and 3 only
- D: 1, 2 and 3
Related Practice Questions:
- Let $S_1$ and $S_2$ be two disjoint, non-empty convex sets in $\mathbb{R}^n$. Under which of the following conditions is there guaranteed to exist a hyperplane that strictly separates $S_1$ and $S_2$?
- Let the primal linear programming problem be: Maximize $Z = c^T x$ subject to $Ax \le b, x \ge 0$. If this primal problem has an unbounded optimal objective value, then which of the following statements is always true regarding its dual problem?
- Let $S = \{(x, y) \in \mathbb{R}^2 \mid x^2 + y^2 \le 9\}$ be a convex set in $\mathbb{R}^2$. The set of all extreme points of $S$ is given by:
- In a linear programming problem with $3$ independent equality constraints and $5$ variables (including slack/surplus variables), what is the maximum possible number of basic solutions?